General information
The measure is specifically dedicated to the mitigation and better management of hydrogeological risk, in particular with reference to the restoration of damaged infrastructure and the reduction of residual risk.
In detail
- about 13.5 million euros have been earmarked for so-called "existing" works, i.e. works that had already begun as at 31 December 2021: these are fourteen interventions dedicated to hydraulic systems, rockfall and avalanche barriers and vallatomi aimed at restoring and making safe the provincial territory following the exceptional event of October 2018 (Vaia)
- approximately €14.1 million has been allocated to Trentino for the implementation of four so-called 'new' intervention projects. Part of it is earmarked for risk mitigation works along Provincial Road 14 leading to Lake Tovel in Val di Non and part is earmarked for prevention works along the Adige riverbank.
Goals
Restoring damaged infrastructure and reducing residual risk in disaster-stricken areas on the basis of local investment plans.
Target: the implementation of interventions in Trentino contributes to the national target of fully completing the financed works by June 2026.
Start date
05/09/2019
End date
30/04/2026
Project duration notes
The projects have different start and end dates, but all between September 2019 and April 2026.