Flood and hydrogeological risk management: 'in place' projects

Mission 2 - Component 4 - Investment 2.1b

Implement a set of interventions that combine structural measures (securing against landslides or flood risk reduction in metropolitan areas) with other measures focusing on upgrading, monitoring and prevention of emerging risks.

General information

The measure is specifically dedicated to the mitigation and better management of hydrogeological risk, with particular reference to activities for the restoration of damaged infrastructures and the reduction of residual risk.

Approximately EUR 13.5 million has been earmarked for so-called 'existing' works, i.e. already underway as at 31 December 2021: these are fourteen interventions dedicated to hydraulic systems, rockfall and avalanche barriers and vallatomi aimed at restoring and securing the provincial territory following the exceptional event of October 2018 (Vaia).

Goals

Restoring damaged infrastructure and reducing residual risk in disaster-stricken areas on the basis of local investment plans.

Target: the implementation of interventions in Trentino contributes to the national target of fully completing the financed works by 2025.

Start date

05/09/2019

End date

31/12/2025

Project duration notes

The projects have different start and end dates, but all between September 2019 and December 2025.

Reference documents

Parole chiave

Planning and funding

Planning tool

NRRP National Recovery and Resilience Plan
Mission 2 – Green revolution and ecological transition
C4 – Protection of the territory and water resources
I2.1.B – Measures for flood risk management and hydrogeological risk reduction

The implementation of the NRP in Trentino fits coherently into the programme framework for sustainable provincial development, according to the policies identified in the provincial Economic and Financial Document and its Update Note.

Source of funding

European funds
Extraordinary funds
NGEU – Next Generation EU

Total budget

£ 18,219,502.78

Budget notes

PNRR funding: € 13,509,332.96

State resources for Emergency Vaia: € 4,710,163.82

Monitoring

The 'Outstanding Interventions' are technically concluded with the exception of CUP C27H20000480004, administratively the expropriation phase remains to be completed.

Communication

Unique project code – CUP

codice
C17H19001640004 Work No. S-921 Construction of rockfall barriers from km 16.9 to km 18
C17H19001650004 Work no. S-923 Construction of rockfall barriers from km 89 to km 90
C97H20000630004 Work no. S-963 Construction of Valli tomo to protect the roadway of the S.S. 48 delle Dolomiti between progressions 41.6 and 41.8
C37H20000510004 Work S-966 Weather events 2018 Raising of Ceggio bridge on SP 65 Panoramica Valsugana
C27H20000490004 Work S-969 Weather events 2018 Construction of rockfall barriers to protect the SS 48 of the Dolomites from km 37.800 to km 38.800 approx.
C17H20000610004 Opera S-970 Meteorological events 2018 Setting up of rockfall barriers to protect the SP 56 road in Caoria from km 0.900 to km 1.800 approx. and hydraulic repair of the bridge
C57H20002170003 Emergency road safety works to repair and replace damaged rockfall barriers from km. 25+000 to km. 27+100 of the S.S. 350 di Folgaria e di Val d'Astico in the municipality of Folgaria
C97H19001340004 Work no. S-919 Meteorological events 2018 Construction of avalanche and rockfall barriers from Km. 45+830 to Km. 45+900 approx. of the S.S. 48 delle Dolomiti LOT 3
C27H19001200004 Work no. S-919 Meteorological events 2018 Construction of avalanche barriers and rockfall barriers from Km. 40+400 to Km. 40+700 approx. of the S.S. 48 delle Dolomiti LOT 2
C27H20000480004 Work S-965 Weather events 2018 Protection east tunnel entrance on S.S. 50 del Grappa and Passo Rolle from km 105.000 to km 105.700
C97H20000640004 Work S-929 Weather events 2018 Construction of rockfall and avalanche barriers from km 4.400 to km 4.800 on the SS 346 San Pellegrino Pass
C27H19001190004 Work no. S-919 Construction of avalanche and rockfall barriers from km. 40+400 to km. 45+900 approx. LOT 1
C17H20000620004 Work no. S-972 Weather events 2018 Construction of rockfall barriers to protect the SP 31 Manghen pass from km 16.600 to km 17.600 approx.
C77H20000570004 Opera S-971 Meteorological events 2018 Construction of rockfall barriers to protect the SP 31 Manghen pass from km 7,600 to km 14,900 approx.