Construction of the inter-municipal black water sewer San Zeno - Dermulo

Mission 2 Component 4 Investment 4.4

Completing unfinished sewerage networks and building new treatment plants

General information

The modernisation of the sewage and purification network is a major issue in Italy, which has led to some infringement proceedings by Europe. The plants will follow, where possible, the 'green factories' model, so as to allow the recovery of energy and sludge and reuse the purified wastewater for industrial or irrigation purposes.

For Trentino, two project proposals submitted by the Province of Trento to the Ministry were considered admissible, including the'Construction of the inter-municipal black water sewer collector San Zeno - Dermulo (TN)'.

The intervention consists in the construction of a 2,900 m black sewer collector to serve the village of San Zeno and the accommodation area called Le Plaze, straddling two municipal territories (San Zeno and Predaia). The intervention allows the decommissioning of an old Imhoff tank, now inadequate for the needs of the present users, and the connection to the provincial purification system with final discharge at the existing biological purification plant in Taio.

Goals

Reduction in the number of agglomerations with inadequate sewerage networks and urban waste water collection and treatment systems.

Start date

09/08/2023

End date

31/12/2025

Project duration notes

The date of 31/12/2025 refers to the acceptance of the work.

Reference documents

Parole chiave

Planning and funding

Planning tool

NRRP National Recovery and Resilience Plan
Mission 2 – Green revolution and ecological transition
C4 – Protection of the territory and water resources
I4.4 – Investments in sewerage and purification

The implementation of the NRP in Trentino fits coherently into the programme framework for sustainable provincial development, according to the policies identified in the provincial Economic and Financial Document and its Update Note.

Source of funding

NGEU – Next Generation EU

Total budget

£ 1,989,150.00

Budget notes

PNRR funding: € 1,975,000.00

Supplementary PAT funding: € 14,150.00

Monitoring

Final project approved and subject to positive verification.

Executive project approved on 22 May 2024.

The project is now in the construction phase (start 10.09.2024).

Unique project code – CUP

codice
C64E13000140003