Implementation and reporting PNRR facades - Palù del Fersina

  • Active

Implementation of projects financed by the PNRR under the 'borgo' project for the municipality of Palù del Fersina - Intervention 27 - contributions for the renovation of facades or entire private buildings for residents

Description

If your project is among those financed by the public notice for the redevelopment of façades or entire private buildings for residents, intervention 27 of the borgo project - Palù del Fersina - the strength of the minority: rebirth of a Germanic village south of the Alps within the framework of the PNRR Mission 1 - Component 3 - Investment 2.1 - Line of action A, you can

  • possibly request the payment of progress payments (SAL) up to a maximum of 70% of the grant awarded
  • submit requests for project changes where necessary
  • request the settlement of the financing by submitting the works report and then request the payment of the grant or the balance, if any

The entire implementation phase is governed by the vademecum approved by Resolution of the Provincial Council no. 1314 of 5 September 2025.

Who it's for

Beneficiaries to whom the grant was awarded under the PNRR public notice for the renovation of facades or entire private buildings for residents for the municipality of Palù del Fersina

What to do

The request, digitally signed by the proposer, must be sent exclusively to serv.urbanistica@pec.provincia.tn.it using the approved forms.

Special cases

The documentation submitted may be supplemented, if necessary, at the request of the office in charge, depending on the case and the technical-administrative investigation.

What you need

Documents to be submitted

There is a specific form for each request:

SAL (State of Works Progress)

  • Annex 1 - Application for SAL payment
  • Annex 3 - Periodic Report
  • Annex 5 - Pantouflage declaration
  • Annex 7 - Communication of dedicated current account
  • Annex 8 - Declaration of compliance with DNSH
  • Annex 9 - Declaration of conflict of interest
  • Annex 11 - Declaration of start of work (if not already submitted)
  • Annex 6 - Statement of account
  • Annex 4 - Declaration of past invoices (only for electronic invoices not showing CUP)
  • Copy of the invoices listed in Annex 6
  • Photographic documentation of work progress and fulfilment of E.U. reporting obligations

Project variation request

  • Annex 10 - Project variation application
  • Proposed variations report

Statement of work and request for balance payment

  • Annex 2 - Application for balance payment
  • Annex 6 - Statement of Accounts
  • Annex 3 - Periodic Report
  • Annex 4 - Declaration of past invoices (only for electronic invoices not showing CUP)
  • Annex 5 - Declaration pantouflage
  • Annex 7 - Declaration of dedicated current account
  • Annex 9 - Declaration of conflict of interest
  • Annex 8 - Declaration of compliance with DNSH
  • Annex 11 - Declaration of start of works (if not already submitted)
  • Annex 12 - Declaration of end of works
  • Copy of the invoices listed in Annex 6
  • Copy of regular execution certificates
  • Photographic documentation of end of works and fulfilment of E.U. reporting obligations

Forms

Timeframes and deadlines

 

30 days

Maximum no. of waiting days

The 30 days run from the submission of the application. For design variations, approval or rejection will be communicated within 20 days of receipt of the documentation.

Costs

FREE

Contacts

Contatti di Ufficio politiche di incentivazione per la valorizzaz. paesaggistica

Email - Segreteria:
serv.urbanistica@provincia.tn.it

Pec - Segreteria:
serv.urbanistica@pec.provincia.tn.it

Telefono - Segreteria:
0461.492712

Telefono - Segreteria:
0461.497044

Fax - Segreteria:
0461.497079

monday
09.00, 12.00
tuesday
09.00, 12.00
wednesday
09.00, 12.00
thursday
09.00, 12.00
friday
09.00, 12.00
Validity start date 01/01/2024

Sito web OpenCity Italia · Site editors access