Towards a safe and sustainable hospital

Mission 6 - Component 2 - Investment 1.2

Bringing hospital facilities up to earthquake-proof standards

General information

This investment consists of seismic upgrades in the light of the new regulatory framework on the subject. Hospitals play a strategic role, both for their fundamental function of rescuing the population and for their greater level of exposure in the event of seismic events, as they house a very large number of people with heterogeneous reaction capacities.

Specifically, this involves:

  • 2 structural interventions with PNRR funds for the restructuring and seismic improvement of the Borgo Valsugana Hospital and the Perusini Pavilion in Pergine Valsugana;
  • 4 structural interventions with PNC funds for the current RSA Vannetti of Rovereto and for pavilions A and B of the Arco hospital.

Goals

Improve the safety of hospital buildings by adapting them to the current standards for construction in seismic areas.

Provincialtarget: 6 interventions

Start date

12/06/2023

End date

30/12/2026

Project duration notes

PNRR projects will be completed by June 2026; PNC projects will be completed by December 2026.

Reference documents

Parole chiave

Planning and funding

Planning tool

NRRP National Recovery and Resilience Plan
CNP Complementary National Plan
Mission 6 – Health
C2 – Innovation, research and digitalisation of the national health service
I1.2 – Towards a safe and sustainable hospital

The implementation of the NRP in Trentino fits coherently into the programme framework for sustainable provincial development, according to the policies identified in the provincial Economic and Financial Document and its Update Note.

Source of funding

NGEU – Next Generation EU
National funds
Provincial funds

Total budget

£ 18,349,039.41

Budget notes

PNRR Funding: € 5,225,791

PNC Funding: € 11,860,975

Monitoring

Work on the Perusini building in Pergine Valsugana (PNRR) has been completed.

Work at the Borgo Valsugana hospital (PNRR) is scheduled to begin in March 2026.

Work at the former RSA Vannetti in Rovereto (PNC) is in progress.

Work on the demolition of pavilion A1 of the Arco hospital (PNC) is scheduled to begin by the end of October 2025.
Work on the reconstruction of Pavilion A2 (PNC) is scheduled to begin by the end of January 2026.
Work on the seismic improvement of Pavilion B (PNC) is scheduled to begin by the end of November 2025.

Unique project code – CUP

codice
B35F25000160006 Borgo Valsugana Hospital - earthquake-proof adaptation 1st floor
B75F23000250006 RSA Vannetti di Rovereto - anti-seismic upgrading North-West wing (Block B)
B35F23000200001 Perusini Pavilion in Pergine Valsugana - structural reinforcement
B56G25000210001 Arco hospital (demolition of Pavilion A)
B55F25000130001 Arco hospital (reconstruction Pavilion A)
B56G25000220001 Arco Hospital (seismic improvement Pavilion B)