General information
The Community Centre will serve as a permanent hub to ensure the promotion andprevention of ill health and the provision of care for the local community, particularly for those with chronic conditions, and will also be equipped with IT infrastructure (telemedicine) and a range of specialist medical equipment. It will serve as a single point of access to local health and social care services, working in coordination with the hospital network to ensure local services for residents.
The organisational model, already in place in the area, will be further strengthened through structural investments that will affect, to varying degrees, existing facilities (similar in function to the Community Centres), as well as facilities that will be used for this purpose, including newly built ones.
Community Centres are planned for Ala, Cles, Borgo Valsugana, North Trento, Malé, Sen Jan di Fassa, Riva del Garda, Rovereto, Pergine Valsugana, Mezzolombardo and South Trento.
Goals
To provide an integrated response to basic care needs, with permanent points of contact for thelocalpopulation that ensurethe community is properly looked after, including through a blood sampling centre, a range of specialist and basic diagnostic equipment, and an IT infrastructure.
Target: a minimum of10 Community Centres, whilst also ensuring energy efficiency.
Start date
18/02/2022
End date
31/05/2026
Project duration notes
The projects have different start and end dates, but all fall between February 2022 and March 2026.