Community Homes

Mission 6 – Component 1 – Investment 1.1

Establish at least 10 Community Centres as a tool for coordinating all health and social care services at local level by providing a single point of access to healthcare services in conjunction with the hospital network, as well as by establishing the single point of access (PUA) for multidimensional assessments of social and healthcare needs with social and care services, in coordination with the initiatives proposed in Mission 5.

General information

The Community Centre will serve as a permanent hub to ensure the promotion andprevention of ill health and the provision of care for the local community, particularly for those with chronic conditions, and will also be equipped with IT infrastructure (telemedicine) and a range of specialist medical equipment. It will serve as a single point of access to local health and social care services, working in coordination with the hospital network to ensure local services for residents.

The organisational model, already in place in the area, will be further strengthened through structural investments that will affect, to varying degrees, existing facilities (similar in function to the Community Centres), as well as facilities that will be used for this purpose, including newly built ones.

Community Centres are planned for Ala, Cles, Borgo Valsugana, North Trento, Malé, Sen Jan di Fassa, Riva del Garda, Rovereto, Pergine Valsugana, Mezzolombardo and South Trento.

Goals

To provide an integrated response to basic care needs, with permanent points of contact for thelocalpopulation that ensurethe community is properly looked after, including through a blood sampling centre, a range of specialist and basic diagnostic equipment, and an IT infrastructure.

Target: a minimum of10 Community Centres, whilst also ensuring energy efficiency.

Start date

18/02/2022

End date

31/05/2026

Project duration notes

The projects have different start and end dates, but all fall between February 2022 and March 2026.

Reference documents

Planning and funding

Planning tool

NRRP National Recovery and Resilience Plan
Mission 6 – Health
C1 – Proximity networks, facilities and telemedicine for local healthcare
I1.1 – Community Homes and personal care

The implementation of the PNRR in Trentino is fully aligned with the provincial policy framework for sustainable development, in accordance with the policies set out in the Provincial Economic and Financial Document and the related Update Note.

Source of funding

European funds
Extraordinary funds
NGEU – Next Generation EU
Provincial funds

Total budget

£ 22,053,554.12

Budget notes

PNRR funding: €14,996,600.00 
PAT funding: €7,056,954.12

Monitoring

The target has been met for the Community Centres in Ala, Malé, Mezzolombardo, Trento Sud, Rovereto, Riva del Garda and Borgo Valsugana.

For the remaining Community Homes in Sen Jan di Fassa, Pergine Valsugana, Trento Nord and Cles, the procedures are currently being finalised and are expected to be completed shortly.

Unique project code – CUP

codice
B17H21006930001 Community Centre in Malé
B32C21002100001 Community Centre in Pergine Valsugana
B35F23000190006 Community Centre in Borgo Valsugana
B62C21001740001 Community Centre in Sen Jan Di Fassa
B68I21001420004 Community Centre in North Trento
B72C21001640001 Community Centre in Rovereto
B78I21002200001 Community Centre in Cles
B82C21001880001 Community Centre in Riva del Garda
B98I21002140001 Community Centre in Ala
B82C24000610003 Community Centre in Mezzolombardo
B62C24000580003 Community Centre in South Trento