This content is translated with an automatic translation tool: the text may contain inaccurate information.

Community Houses

Mission 6 - Component 1 - Investment 1.1

Activating 10 Community Houses as a coordination tool of all health and social-health services at territorial level through the provision of a single access point for health services in connection with the hospital network as well as through the location of the single access point (PUA) for multidimensional assessments of social-health needs with social and welfare services, in coordination with the initiatives proposed in Mission 5.

General information

The Community House will be an ongoing point of reference to ensure health promotion, prevention and care for the community of reference, especially for the chronically ill, and will also be equipped with IT infrastructure (telemedicine) and multi-specialist equipment. It will be a single access point for health and social-health services in the area, therefore, in coordination with the hospital network, with the aim of guaranteeing proximity services to residents.

The organisational model, which is already present in the area, will be further strengthened with structural investments that will involve, to varying degrees, existing structures (similar in function to the Community Homes), as well as structures that will be used for this function, including newly built ones.

The Case della Comunità are planned in Malé, Predazzo, Pergine Valsugana, Borgo Valsugana, Sen Jan di Fassa, Trento nord, Rovereto, Cles, Riva del Garda and Ala.

Goals

To provide an integrated response to basic care needs, with continuous points of reference for the population to ensure that the community is taken care of, also by means of a collection point, basic multi-specialist and diagnostic equipment, and an IT infrastructure.

Target: 10 Community Houses (3 to be built, 7 to be renovated), also ensuring energy efficiency.

Start date

18/02/2022

End date

31/03/2026

Project duration notes

The projects have different start and end dates, but all fall between February 2022 and March 2026.

Reference documents

Planning and funding

Planning tool

NRRP National Recovery and Resilience Plan
Mission 6 – Health
C1 – Proximity networks, facilities and telemedicine for local healthcare
I1.1 – Community Homes and personal care

The implementation of the NRP in Trentino fits coherently into the programme framework for sustainable provincial development, according to the policies identified in the provincial Economic and Financial Document and its Update Note.

Source of funding

Provincial funds
NGEU – Next Generation EU

Total budget

£ 31,225,600.00

Budget notes

PNRR funding: € 14,996,600.00
PAT funding: € 16,229,000.00

Monitoring

Work on the Casa della Comunità in Ala is complete.
Work has begun on the Community Houses in Cles, Borgo Valsugana, Trento, Malé, San Jean di Fassa and Predazzo.
For the Rovereto Community House, work is scheduled to begin in the spring of 2025.
The start of works for the Community Houses in Pergine Valsugana and Riva del Garda are conditional on the completion of other works on the same buildings and, respectively, the works for structural reinforcements and for the Community Hospital in Pergine Valsugana and the fire-prevention works for the building identified in Riva del Garda.

Communication

PaT notices, press releases, further information

Images

Related projects

Links to external websites

Unique project code – CUP

codice
B17H21006930001 Community House in Malé
B25F21002200001 Community House in Predazzo
B32C21002100001 Community House in Pergine Valsugana
B35F23000190006 Community House in Borgo Valsugana
B62C21001740001 Community House in Sen Jan Di Fassa
B68I21001420004 Trento Nord Community House
B72C21001640001 Community House in Rovereto
B78I21002200001 Community House in Cles
B82C21001880001 Community House in Riva Del Garda
B98I21002140001 Community House in Ala
Sito web OpenCity Italia · Site editors access