Community Homes

Mission 6 – Component 1 – Investment 1.1

Establish at least 10 Community Centres to serve as coordination hubs for all health and social care services at local level, ensuring a single point of access to healthcare services, in conjunction with the hospital network, and the provision of a single point of access (PUA) for the multidimensional assessment of social and healthcare needs, integrated with social and welfare services and the interventions under Mission 5.

General information

The Community Centre serves as a permanent point of reference to ensurehealth promotion andprevention, as well as the provision of care for the local community, particularly for those with chronic conditions; it is also equipped with IT infrastructure (telemedicine) and a range of specialist medical equipment. It serves as a single point of access to local health and social care services, in coordination with the hospital network, with the aim of providing local services to residents.

The organisational model, already in place in the area, has been further strengthened through structural investments which have, to varying degrees, involved existing facilities (similar in function to the ‘Case della Comunità’) as well as newly built facilities designated for this purpose.

Goals

To provide an integrated response to basic healthcare needs, with ongoing points of contact for the population, in order to ensure thecare of the local community, including through a blood-taking centre, a range of specialist and basic diagnostic equipment, and an IT infrastructure.

Target: a minimum of10 Community Centres, whilst also ensuring energy efficiency.

Start date

18/02/2022

End date

31/05/2026

Project duration notes

The projects had different start and end dates, but all fell within the period from February 2022 to May 2026.

Reference documents

Planning and funding

Planning tool

NRRP National Recovery and Resilience Plan
Mission 6 – Health
C1 – Proximity networks, facilities and telemedicine for local healthcare
I1.1 – Community Homes and personal care

The implementation of the PNRR in Trentino fits seamlessly within the provincial framework for sustainable development, in line with the policies set out in the Provincial Economic and Financial Document and the related Update Note.

Source of funding

European funds
Extraordinary funds
NGEU – Next Generation EU
Provincial funds

Total budget

£ 21,936,383.89

Budget notes

PNRR funding: €14,996,600.00

Monitoring

The project has met and exceeded its target of 10 Community Centres, with 11 facilities now operational in the areas ofAla, Cles, Borgo Valsugana, North Trento, Malé, Sen Jan di Fassa, Riva del Garda, Rovereto, Pergine Valsugana, Mezzolombardo and South Trento.

The projects carried out have helped to strengthen the local healthcare network by upgrading and adapting existing facilities and establishing new centres, equipped with services and resources to facilitate integrated care and localised treatment.

Today, the Community Centres serve as key points of reference for accessing health and social care services, helping to strengthen local care provision and continuity of care, particularly for people with chronic conditions.

Communication

Avvisi PaT, comunicati stampa, approfondimenti

Images

Related projects

Links to external websites

Unique project code – CUP

codice
B17H21006930001 Community Centre in Malé
B32C21002100001 Community Centre in Pergine Valsugana
B35F23000190006 Community Centre in Borgo Valsugana
B62C21001740001 Community Centre in Sen Jan Di Fassa
B68I21001420004 Community Centre in Trento North
B72C21001640001 Community Centre in Rovereto
B78I21002200001 Community Centre in Cles
B82C21001880001 Community Centre in Riva del Garda
B98I21002140001 Community Centre in Ala
B82C24000610003 Community Centre in Mezzolombardo
B62C24000580003 Community Centre in South Trento