Description
Aid granted to support investment by businesses in the energy transition,environmental protection,the circular economy andenergy efficiency.
What is funded
It is possible to obtain a grant for investment initiatives relating to:
- wood biomass plants for production processes (sub-measure C1);
- district heating systems (sub-measure C2);
- high-efficiency cogeneration plants for production processes (sub-measure C3);
- extensive refurbishment of building envelopes – non-accommodation sector facilities (sub-measure C4);
- extensive refurbishment of the building envelope – accommodation sector facilities (sub-measure C5);
- biogas cogeneration plants (sub-measure C6);
- renewable hydrogen plants (sub-measure C7);
- photovoltaic systems (sub-measure C8);
- investments in environmental protection (sub-measure C9);
- improvements to the energy efficiency of production processes (sub-measure C10).
Investment projects must commence after the date of application submission, with the exception of projects relating to wood-based biomass plants for production processes, high-efficiency cogeneration plants for production processes, biogas cogeneration plants, renewable hydrogen plants and photovoltaic systems. In such cases, work on the project may commence prior to the date of application submission; however, expenditure must still be incurred after the date of application submission.
Applications are assessed through an evaluation procedure.
Incentives and expenditure limits
View the incentive measures and expenditure limits for each sub-measure here.
The incentive is granted under an exemption scheme pursuant to Commission Regulation (EU) No 651/2014 of 17 June 2014.
Applications involving expenditure in excess of 10 million euros are not eligible for support.
Please note!
- For applications with eligible expenditure exceeding 2.5 million euros, the incentive is reduced as set out in point 9, paragraph 2, of the specific environmental provisions.
- Small-scale investment projects relating to biomass boilers, high-efficiency cogeneration units and photovoltaic systems may be eligible for supportunder the annual ‘Crescita Trentino’ aid scheme – Provincial Law 6/2023 – provided they fall within the permitted limits and conditions.
Restrictions
Specific obligations are set out in the general provisions applicable to all projects and in the specific environmental provisions relating to individual projects.
These include the following obligations:
- to complete the project;
- to ensure the operational unit remains within the province and that the assets benefiting from the scheme are not diverted from their intended purpose;
- employment-related obligations;
- economic and financial obligations.
Investment projects with eligible expenditure exceeding 1 million euros are also subject, for the purposes of granting the incentive, to the signing of an agreement between the Province and the company applying for the incentive. The agreement may include further obligations and conditions.
Reporting
Initiatives eligible for the incentive must be completed by 31 December of the third year following the year in which the incentive was granted.
A report on the expenditure incurred for which the incentive was claimed must be submitted within one year of the initiative’s completion dateas specified in the grant decision.
Extensions to the deadlines for completion of the initiative and/or reporting of expenditure may be granted subject to the submission of a reasoned application to the assessing body.